Bournemouth Pier Structural Works

发布时间 所属地区 所属机构 语言
2025年03月08日 -- -- 英语 (English) 中文

Published date: 20 January 2025

Last edited date: 7 March 2025

Open opportunity - This means that the contract is currently active, and the buying department is looking for potential suppliers to fulfil the contract.

Watch this notice Print this notice
Closing: 30 July 2025, 2pm

Contract summary

Industry

  • Engineering works and construction works - 45220000

  • Structures construction work - 45223000

  • Reinforced-concrete structures - 45223500

  • Show additional CPV codes for this notice
  • Pier construction work - 45241300

  • Sea wall construction work - 45243300

  • Concrete repair work - 45262330

  • Location of contract

    South West

    Value of contract

    £8,000,000 to £8,750,000

    Procurement reference

    BOURN001-DN755872-14630995

    Published date

    20 January 2025

    Closing date

    30 July 2025

    Closing time

    2pm

    Contract start date

    1 April 2026

    Contract end date

    31 December 2027

    Contract type

    Works

    Procedure type

    Open procedure (above threshold)

    What is an open procedure (above threshold)?

    Any interested supplier may submit a tender in response to an opportunity notice.

    This procedure can be used for procurements above the relevant contract value threshold.

    Contract is suitable for SMEs?

    Yes

    Contract is suitable for VCSEs?

    No


    Description

    The structural works are to extend the life of the pier by at least 25 years. The scope includes undertaking concrete repairs, installing Impressed Current Cathodic Protection (ICCP) system and removal of timber landing stages.

    Due to budget constraints, the Council are considering 3 options, these being: -
    • Option A: All Concrete Works Only
    Concrete works only. No removal of any of the timber landing stages.
    • Option B: All Concrete Works and Part Timber Landing Stage Removal
    Concrete works and the complete removal of the Northern and Small Boat timber landing stages only.
    • Option C: All Concrete Works and All Timber Landing Stage Removal
    Concrete works and complete removal of all of the timber landing stages
    All works will be covered by a single NEC4 ECC Option A contract (incorporating a Bill of Quantities for concrete repair works).

    The Councils preferred option is Option C, if affordable. If this is not achievable, then the Council will consider Option B and if that isn't affordable then Option A.

    Suppliers can bid to any or all of the 3 options.

    The specifications which outline the requirements for this contract are contained with the following document 'Bournemouth Pier Structural Works - Document Schedule 16.01.2025'

    The successful Bidder will be expected to commence the works in May 2025 and will be required to ensure the works are completed by December 2026 (not including defects period).


    More information

    Previous notice about this procurement

    Bournemouth Pier Structural Works

  • Opportunity
  • Published 20 January 2025, last edited 5 February 2025
  • Links

  • https://procontract.due-north.com/Advert?advertId=08503e21-36d7-ef11-8133-005056b64545&p=696a9836-1895-e511-8105-000c29c9ba21
  • Link to Advert for Suppliers to Access Tender Documents
  • Additional text

    Suppliers interested in this opportunity can access the full procurement documentation by visiting BCP Council's Tendering system www.supplyingthesouthwest.org.uk

    Suppliers should search for the opportunity through Supplying the South West. There are further details of the opportunity on the advert published on www.supplyingthesouthwest.org.uk and instructions on how suppliers can access the procurement documentation for completion.

    Responses to the opportunity must be submitted electronically through www.supplyingthesouthwest.org.uk before the deadline shown on the system.

    If you are unable to access the advert for the opportunity through www.supplyingthesouthwest.org.uk please contact the Council using the contact details provided.


    How to apply

    Follow the instructions given in the description or the more information section.


    About the buyer

    Contact name

    Strategic Procurement Team

    Address

    BCP Council
    Civic Centre, Bourne Avenue
    Bournemouth
    BH2 6DY
    England

    Telephone

    +44 1202128989

    Email

    procurement@bcpcouncil.gov.uk

    Website

    https://www.bcpcouncil.gov.uk


    Share this notice

    Is there anything wrong with this page?

    温馨提示:本网站为您提供准确和及时的招投标信息,但招投标信息存在着变更的可能,请您务必在交易前向招标代理机构或招标人咨询投标详细要求,有关招标的具体要求及情况以招标代理机构或招标人的解释为准。
    如果您对这篇招标信息有任何补充或修改建议,请告知我们。

    猜你喜欢

    加载中...

    广告